During a check to make sure that the improvements required had been made
In November 2013 we asked the provider for an updated action plan and a report on their progress towards achieving compliance. It was agreed that a follow up visit to check compliance would not be proportionate in view of the provider's imminent application to cancel their registration of the location. Further information was received from the provider in early December 2013 that demonstrated continued improvement. The provider also anticipated that the prison would close as planned by the end of December 2013. They told us that by mid December they expected there to be only 30 people receiving their service.
We found that the provider had carried out their planned improvements to ensure compliance with outcomes 9 (management of medicines) and 14 (supporting staff).